A project team discovers that a key project component has a significantly higher carbon footprint than initial...

ProcessGovernancePlanningHybrid

A project team discovers that a key project component has a significantly higher carbon footprint than initially estimated. The project is 60% complete. What should the PM do?

  • A.Continue as planned since the project is too far along to change.
  • ✓ Correct B.Raise a change request to evaluate lower-carbon alternatives for the remaining work, assess schedule and cost implications, and update the sustainability plan.
  • C.Halt the project immediately until a green alternative is found.
  • D.Offset the carbon through tree planting without changing the project.

Correct answer: B

Explanation

The correct answer is B. Even at 60% complete, the remaining work may offer chances to reduce the carbon footprint. A change request lets the team evaluate lower-carbon alternatives for that work, assess schedule and cost impacts, and update the plan through proper governance. Continuing unchanged (A) ignores a significant problem, halting the project (C) is excessive, and relying only on offsets (D) avoids reducing the actual impact.