Due to a recent budget reduction, two team members were released from an agile team. The customer is still exp...

ProcessFinanceDeliveryAgile

Due to a recent budget reduction, two team members were released from an agile team. The customer is still expecting early results for the project. Which two actions should the project manager take to align customer expectations? (Choose two)

  • A.Review the impediments log with the customer.
  • ✓ Correct B.Ask the product owner to review the prioritized backlog with the customer.
  • C.Ask the agile team to review and update the quality management plan with thecustomer.
  • ✓ Correct D.Ask the agile team to review the updated sprint velocity with the customer.
  • E.Send a detailed project management plan to the customer.

Correct answer: B, D

Explanation

The correct answers are B and D. With fewer team members, delivery capacity has changed, so the customer's expectations must be realigned: the team shares the updated velocity, and the product owner reviews the prioritized backlog with the customer so the most valuable items come first. Reviewing the impediments log (A) or the quality plan (C) does not reset expectations, and sending a detailed management plan (E) is one-way and does not reprioritize work.